Mass Transportation Authority - Phase VI

Out-County Transit Centers

Project Summary Points:

Mt. Morris Site:

Building Area: 9,219 s.f. total

  • Office - 2,019 s.f.
  • Garage - 7,200 s.f.

Project Estimate:  $1,217,022.50

Actual Cost:  $1,245,895.00

Contract Dated: July 23, 2003

Scheduled Project Completion Time: 210 Days

Completed November, 2004

 

Grand Blanc Site:

Building Area: 13,026 s.f. total

  • Office - 4,026 s.f.
  • Garage - 9,000 s.f.

Project Estimate:  $1,915,618.50

Actual Cost:  $1,891,993.00

Contract Dated: July 23, 2003

Scheduled Project Completion Time: 210 Days

Completed November, 2004

 

 

 

Fenton & Swartz Creek Sites:

Building Area: 13,463 s.f. total

  • Office - 4,026 s.f.
  • Garage - 8,957 s.f.

Project Estimate:  $1,645,000.00

Actual Cost:  $1,654,638.00 - Fenton

$1,574,255 - Swartz Creek

Contract Dated: March 1, 2006 - Fenton

November, 2007 - Swartz Creek

Scheduled Project Completion Time: 172 Days

Completed May, 2007 - Fenton

November, 2008 - Swartz Creek